1-10-18
                                                        SOUTHWEST REGIONAL WATER DISTRICT FUTURE WATER RESOURCE DEVELOPMENT
                                                                         DAKOTA SANDSTONE WELL DRILLING PROJECTS 2016-2018


The past two years SW Regional Water has consulted and worked with engineers, well drillers, IDNR, and hydrologists to identify and plan drilling sites to construct new test wells in the Dakota sandstone aquifer in central Montgomery county.In 2016 - 4 new core sample drilling sites were secured with easements and two of those sites had test wells constructed  
on them after core sampling and sieve analysis was completed.

 The North Test Well located next to a SWRWD pumping station was drilled to a total depth of 215 feet. The layer of sandstone was 60 Feet deep, and the test well casing was 6” in diameter. Pumping tests were completed in March and May of 2017 at 363 GPM for 73 hours and 369 GPM for 31 hours. 

 A hydrologist report was issued in August 2017 and provided recommendations to construct a finish Water Production Well on 1 of the 2 Test Well sites. Iowa DNR completed a future well site evaluation at this north Test Well site. In November 2017 the SWRWD purchased 4 Acres at this North Test Well site for
a future 750 GPM production well water supply. Water quality test samples were collected during the pump testing startup and again at the end of the pump tests. These water samples were sent to certified state labs for analysis. Test results provided information to use for upcoming water treatment engineering design.


                  Dakota Sandstone Well Development Cost Summary
                                                       12-31-17

        Engineering and Surveys --------------------------------$73,008.63
        Drilling and Construction Work ------------------------$136,866.00
        Land Easements and Purchase ------------------------$67,700.00
        Iowa DNR Permits and Legal Costs -------------------$16,116.12
        Land Restoration Costs ------------------------------------$2,436.74

                                                                          TOTAL $296,127.49

 Plans for a new 750 GPM production well to be constructed
and in full operation by 2020 will be located on the south side
of the SWRWD pumping station at the intersection of K Avenue
and 200th Street. 

Geological drilling in October 2016
3-1-18

                                                        SOUTHWEST REGIONAL WATER DISTRICT FUTURE WATER RESOURCE DEVELOPMENT
                                                                DAKOTA SANDSTONE WELL DRILLING PROJECTS JANUARY – MARCH 2018



On November 9, 2017 SW Regional Water entered into
a new well drilling contract with Layne Water Resource
to drill and construct a 2” Observation Well and a 6” Test 
Well in the S.W. ¼ of Section 23 – Red Oak Township. 

On December 5, 2017 Iowa DNR-WS Engineering issued a
Test Well construction and aquifer withdrawal permit. The
DNR withdrawal permit allows a 500 GPM pumping rate for
a maximum of 2.5 million gallons for testing purposes only.

 The 2017 Layne drilling contract was in the amount of
$61,031.00. On January 20, 2018 a 2” Observation well
was test drilled to a depth of 225 Feet. The drilling material
was collected for lab analysis. Clean sandstone was found
from 140 feet to 223 feet. Construction of the 2” Well was
completed on January 24, 2018. A sieve analysis report and
Test Well design was submitted by Layne on March 2, 2018.
The Test Well design would allow for a minimum pumping 
of 200 GPM.


Layne Water Resource -Test Drilling 1-19-18
                Dakota Sandstone Well Development Budget
                          2018 New Drill Site on Highway 34

Engineering Contract ----------------------------$28,000.00
Layne Water Resource Contract -------------$61,031.00
Land Easement and Purchase -------------- -$72,500.00
CRP-MCFSA Contract -------------------------  $2,385.99

                                                               TOTAL $163,916.99

   2” Observation Well completed 1-20-18
Drilled material is collected at 5 to 10 Foot depth readings. The clean sandstone was located from 140 to 223 feet deep. Layne completed a sieve analysis of the sand material and submitted a report and test well design.